White Papers/Reports

Summary of the Final Report on the Secondary System Pipe Rupture at Unit 3, Mihama Nuclear Power Plant (NPP), Kansai Electric Power Co., Inc. (KEPCO)

March 2005
Nuclear and Industrial Safety Agency (NISA)

1. Actions Taken by the Accident Investigation Committee and NISA

Aug. 10, 2004 (the day following the day the accident occurred)

The Accident Investigation Committee was established. Under the Committeefs direction NISA investigated the cause of the secondary system pipe rupture at Unit 3 of the Mihama Nuclear Power Plant.

Sept. 27, 2004

The interim report was prepared, and the Minister gave KEPCO a strict reprimand and ordered the company to comply with the technical standard.

Oct. 2004 to Feb. 2005

NISA conducted additional hearings on each concerned to find the causes of the accident and the measures for preventing the recurrence of the accident.

Mar. 30, 2005

The Accident Investigation Committee held the 10th meeting, and documented the final report. (Two meetings were held in Fukui City.)

@

2. Causes of the Accident

The direct cause of the accident is that the pipe thinning due to erosion and corrosion was overlooked for many years because the pipe in question was mistakenly missing from the inspection list. Further investigations revealed that the root causes of the accident were the poor maintenance management and insufficient quality assurance systems of KEPCO, with the background of the KEPCOfs declined safety culture.

  • Both KEPCO and Mitsubishi Heavy Industries, Inc. (MHI) neglected their duties to check the inspection lists and to establish good communication.
    >>They failed to correct the mistakes in the inspection list that was initially created by MHI.
  • KEPCO's improper management of subcontractors >> The item in question had been mistakenly left out from the inspection list.

  • KEPCO's biased attitude toward process operations >> At some point, noncompliance with technical standards was accepted as normal.

3. Responsibility of KEPCO and Preventive Measures

(1) It is a serious problem that KEPCOfs operation and management of a nuclear power plant is inappropriate in terms of legal liability and external responsibility (improper management of subcontractors), and that their management system is incapable of grasping and rectifying the actual conditions of sites. It is an urgent necessity to improve their maintenance and management capability and to transform their subcontractor management system into a thorough, efficient system. In addition, continued efforts are essential to improve the corporate culture and the sense of values regarding safety.

(2) Based on the points above, KEPCO submitted to NISA the gReport on Preventive Measuresh on March 1 and the gAction Planh on March 25, 2005.

(3) By performing strict nuclear safety inspections, NISA keeps watch on and leads KEPCO to verify whether preventive measures based on the commitments by the president of KEPCO (assignment of personnel to safety-related tasks, investments, etc.) have been properly implemented, and whether the quality assurance system and the corporate culture have fundamentally improved.
@

4. Responsibility of Mitsubishi Heavy Industries and Preventive Measures

(1) The improper maintenance management is the result of a lack of self-discipline as a major manufacturer that plays a vital role in plant construction and maintenance. This has undermined public confidence in not only MHI, but also overall nuclear safety.

(2) Based on the points indicated, MHI prepared the gReport on Preventive Measuresh and the gAdditional report,h and submitted them to NISA on March 1 and March 23, 2005, respectively.

(3) NISA calls on MHI to reflect on its past conduct, and keeps close watch to verify that preventive measures and their improvement activities are properly implemented. NISA expects that MHI will be aware of the companyfs standing as the only PWR (Pressurized Water Reactor) manufacturer in Japan and will take all possible measures to ensure safety (for example, sharing new knowledge of and information on PWR plants with electric utilities).

5. Responsibility and Countermeasures of the Government (NISA)

(1) Regulations about the pipe wall thickness
It was acknowledged that one of the causes of the inappropriate maintenance management is that NISA left the practical method of the pipe wall thickness management to each company.
>> The ministerial ordinances were revised in December 2004, and NISA issued a guideline as a government standard in February 2005.

(2) Regulations for the quality assurance of each company
As new safety regulations went into effect in October 2003, NISA started inspections and directed to each company to conduct autonomous maintenance management and quality assurance activities.
>> Based on the lessons learned from the accident, NISA makes continuous improvements of inspection methods and strongly requires all licensees to conduct maintenance management and quality assurance activities in a strict, thorough manner.

6. Measures for Other Related Issues

(1) Aging management of nuclear power plants
The thinning of pipes is an important phenomenon of deterioration through aging. NISA requests licensees to define the pipe thickness management properly in aging management, and to establish a policy of necessary management, and then to implement these. NISA also monitors and evaluates the status of implementation of measures and policies.
>> NISA encourages the improvement of aging management in line with the standards, reasonable inspection methods, policies, etc., that the Committee for Aging Management will compile around July or August 2005.

(2) Initial actions after an accident
Although it is important to prevent the occurrence of an accident as a matter of course, the initial actions that should be taken are equally important in the sense of risk management to restrain or minimize the spread of damage after an accident.
>> NISA improves and reinforces the initial action system and procedures by coordinating with authorities regarding emergency actions, emergency radiation medical treatment, etc., and by establishing an emergency initial action manual.

(3) Labor safety
The Mihama accident should be examined from the standpoint of labor accident prevention, and preventive measures should be enhanced.
>> It is requested that KEPCO takes measures in such a way as to introduce a labor safety and sanitation management system in a consistent manner.
>> NISA implements consistent measures and policies by coordinating closely with the Ministry of Health, Labour and Welfare, which is in charge of labor safety.

(4) Measures for social and local effects of an accident
The Mihama accident produced various social and local effects: the local residents lost their sense of security in relation to the nuclear power plant, harmful rumors spread and produced a serious impact on economic activities, and so forth.
>> NISA plays an important role in strengthening the safety regulation system, providing accurate information quickly, providing support in the form of road work for transportation in an emergency, etc. In addition, NISA makes continuous efforts to evaluate and analyze social and local effects, and to implement effective measures for accidents and disasters.

Reference:

Summary of preventive measures prepared by The Kansai Electric Power Co., Inc. and Mitsubishi Heavy Industries Inc.

1. Preventive measures by KEPCO

(1) The president declared, gMy and our companyfs mission is to ensure safety.h Under this declaration, five fundamental action policies were announced:

  • We will give the highest priority to safety.
  • We will introduce whatever resources are necessary to ensure safety.

  • We will make continuous improvements to maintenance management, and construct cooperative relationships with manufacturers and cooperating companies.

  • We will make an effort to regain the public confidence of local residents.

  • We will objectively evaluate our safety-related activities and disseminate information on those activities.

(2) Based on these five policies, short-term tasks (face-to-face discussions between the management and workers at sites to improve the safety culture, reinforcement of personnel working at power plants, etc.) to be tackled early in 2005, and mid-term tasks (review of all periodic inspection processes) to be addressed after 2005 were presented.

2. Preventive measures by MHI

(1) Strengthening of maintenance functions to cope with aging
The gMitsubishi Maintenance Committeeh was established to promote overall maintenance activities conducted throughout the Mitsubishi Group. This committee meets twice a year to ensure that proper maintenance activities can be conducted on a long-term basis.

  • Sharing information on the maintenance of primary, secondary and electric systems, enhancing communication among all related departments
  • Providing electricity utilities and the private sector informative guidelines

(2) Company-wide improvements based on the lessons learned
The gIn-house Nuclear Power Reform Committeeh was established in December 2004. It will start conducting systematic, company-wide improvement activities within this year.

  • Measures to improve the Quality Management System (QMS)
  • Measures to improve Corporate Social Responsibility (CSR)

@

White Papers/Reports Top