The IAEA (International Atomic Energy Agency) officials and international experts visited Japan February from 14th to 18th, 2022, to conduct its review mission of safety aspects of handling of ALPS treated water at Fukushima Daiichi Nuclear Power Station (FDNPS). The report, which summarizes the Task Force’s observation to date, was published by the IAEA today.

1. Summary

The review mission of safety aspects of handling of ALPS treated water at FDNPS in February was conducted based on the Terms of Reference (TOR) on a comprehensive framework for cooperation on the handling of ALPS treated water, which was signed with the IAEA last July. The IAEA’s review will be conducted by the IAEA Task Force, which consists of IAEA officials and international experts before, during and after the ALPS treated water discharge. This report describes the findings of IAEA’s review, mainly on the Application Documents for Approval to Amend the Implementation Plan, which was submitted to NRA from TEPCO last December and on the report of assessment of radiological impact on humans and the environment, which was published last November by TEPCO, in accordance with international safety standards for the safety aspects of handling of ALPS treated water.

Ref) The IAEA Task Force includes international experts, serving in a personal capacity, from Argentina, Australia, Canada, China, France, Republic of Korea, the Marshall Islands, Russia, the United States, the United Kingdom, and Vietnam.

2. Key Points of the Report

*There are quotes from the IAEA report (Including some summaries)
The following eight technical items were assessed regarding the characteristics of the ALPS treated water to be discharged, the safety of the discharge process, and radiological impact on the public and the environment.

  1. Crosscutting Requirements and Recommendations
  2. Characterization of discharge and source term
  3. Safety Related Aspects of Systems and Processes for Controlling Discharges
  4. Radiological Environmental Impact Assessment
  5. Regulatory Control and Authorization of Discharges
  6. Source and Environmental Monitoring Programmes
  7. Involvement of Interested Parties
  8. Occupational Radiation Protection

The report includes a summary of the discussion points between the IAEA Task Force and the METI/TEPCO and the initial observations for each technical matter. In relation to the safety of related facilities which is the main contents of the implementation plan it was recognized that an enormous amount of analysis was performed by TEPCO for the conduct of the safety assessment, the level of detail, its comprehensive approach, as well as the fact that a large number of potential single failure events were taken into consideration for the development of the design criteria for the discharge of ALPS treated water. On the radiological impact assessment, it was acknowledged that a comprehensive and detailed analysis was conducted and also noted that the radiological impact on the public was expected to be very low and significantly below the level set by the Japanese regulatory body. The IAEA Task Force noted that a significant amount of work and analysis has been performed to discharge the ALPS treated water, but the results need to be clearly described in writing to demonstrate compliance with relevant requirements in the context of IAEA safety standards.

< Main confirmation items>

1. Characterization of discharge and source term

*1: A method to measure the concentration of alpha emitting radionuclides and inspect for abnormalities.
*2: In the Radiological Impact Assessment Report published by TEPCO last November, in order to make the safety assessment more stringent, calculations were made assuming the existence of radionuclides with short half-lives that are already considered to be significantly absent.

2. Safety Related Aspects of Systems and Processes for Controlling Discharges

3. Radiological Environmental Impact Assessment

4. Regulatory Control and Authorization of Discharges

3. Response to the IAEA report

The points raised by the IAEA Task Force have been reflected in the revised application of  the Implementation Plan, which TEPCO submitted to the NRA, and the report of assessment of radiological impact on humans and the environment. The contents of revised application and revised RIA report are thus further enhanced.
As the discharge plan progresses, and with the findings from the IAEA review, Japan will work to ensure all possible measures are taken to ensure safety and in accordance with international safety standards and all possible measures will be taken to ensure safety.

IAEA Review Meeting in February 2022

4. Related Documents

Division in Charge

Nuclear Accident Response Office, Agency for Natural Resources and Energy